Progress reports

On this page
  1. What progress reports are for
  2. Progress report and payment application compared
  3. Statuses
  4. The Progress reports page
  5. How to create a progress report
  6. How to fill in a progress report
  7. How to submit a progress report
  8. How to accept or return a progress report (office)
  9. How to correct a returned progress report
  10. Folder responsibles and progress reports
  11. Using accepted progress reports
  12. Common questions
  13. Related
WhereProject sidebar Progress reports (Работни карти) in the execution phase, /projects/{project}/progress-reports. A single progress report: /projects/{project}/progress-reports/{card}/draft or .../review.
Who canPermission Progress reports (Работни карти): View (Преглед) to open the list and the progress reports, Edit (Редакция) to create, fill in, submit and start a new draft. Accepting and returning needs Reports (Отчети) at Full access (Пълен достъп). Only the contractor company of a signed contract on its main bill of quantities (BoQ) files progress reports. Paid plan or trial; not included in the Free plan.
RelatedCreating and submitting, Reporting progress, Permission reference

What progress reports are for

On site, foremen and technical supervisors record what was built day by day or week by week. The office later turns that into the official payment application (Отчет) to the client. Progress reports (Работни карти) are that first step inside BuildColab: the site files the quantities, the office checks and accepts them, and the accepted quantities are then reused instead of being retyped.

  • Internal to your company. The other party of the contract (the client) never sees your progress reports: not in its Reports panel, not in the Report Register, not in exports or notifications.
  • No money. A progress report shows quantities only. There is no total, no price column subtotal and no effect on the contract, the payment applications, the financial dashboard or costs.
  • Checked by the office. A progress report counts only after a person with Reports at Full access accepts it.
  • Reused twice. Accepted progress reports can be pulled into a new payment application with New report from progress reports… (Нов отчет от работни карти…), and the construction schedule can show its progress from them.

Progress report and payment application compared

TopicProgress report (Работна карта)Payment application (Отчет)
Who sees itOnly your companyBoth sides of the contract
MoneyNone: quantities onlyQuantities × contract unit prices, with a total
Who decidesYour office: a person with Reports at Full access accepts or returns itThe client approves, counters or rejects it
StatusesDraft, Submitted, Accepted, ReturnedDraft, Submitted, Approved, Rejected, Withdrawn
Negotiation rounds, counter-proposals, withdrawingNoYes
Positions outside the contractNoYes
Excel exportNoYes
NumberingIts own series per contract: Progress report #1, #2…Report #1, #2… per contract
PermissionProgress reports (Работни карти)Reports (Отчети)

Statuses

Status (EN / BG)MeaningWhat can happen next
Draft / ЧерноваThe author is filling in quantities. Changes save automatically.The author (or a person with Full access) clicks Submit (Подай).
Submitted / ПодаденаWaiting for the office. The quantities can no longer be changed.A person with Reports at Full access clicks Accept (Приеми) or Return (Върни). The author cannot withdraw it.
Accepted / ПриетаThe office confirmed the quantities. They now count in the schedule's progress sources and can be used for a payment application.Pulled into a payment application with New report from progress reports…; the Used in column shows every report it was used in. One progress report can be used in more than one payment application.
Returned / ВърнатаThe office sent it back with a comment, shown as Reason for return (Причина за връщане).The author clicks New draft (Нова чернова) to correct it and submit again.

The Progress reports page

Open the project and click Progress reports (Работни карти) in the project sidebar. The entry appears in the execution phase, right after Report Register, and is locked without the Progress reports permission. The page lists every progress report of the project. Everyone with View sees all of them, whoever is their assignee.

Element (EN / BG)What it shows or does
Search boxNarrows the list by text.
FiltersFilter by Contract (Договор), Status (Статус) and Assignee (Отговорник).
New progress report / Нова работна картаCreates a draft. Shown with Progress reports at Edit.
Column Progress report / Работна картаThe number, for example Progress report #3 (Работна карта №3).
Column Contract / ДоговорThe contract (its BoQ name) the progress report belongs to.
Column Status / СтатусDraft, Submitted, Accepted or Returned.
Column Assignee / ОтговорникThe person responsible for the progress report.
Column Submitted on / Подадена наThe date it was submitted, or a dash.
Column Used in / Използвана вEvery payment application it was pulled into, for example #2, #5 (№2, №5). With more than three, the count is shown instead, for example 4 reports (4 отчета), and the tooltip lists them all. A dash if it has not been used.
Preview / ПрегледайOpens the progress report.

When there are none yet, the page says "No progress reports yet." (Все още няма работни карти.)

How to create a progress report

  1. Open the project and click Progress reports (Работни карти) in the project sidebar.
  2. Click New progress report (Нова работна карта).
  3. If your company can file on exactly one contract, the draft is created at once and opens. If there are several, the dialog New progress report opens: choose the contract in Contract (Договор, placeholder "Choose a contract" / „Изберете договор“) and click New progress report.
  4. The draft lists the contract's positions with the contracted quantity. Every quantity for the period is 0.

Progress reports can be filed only on a signed contract where your company is the contractor, on your company's main BoQ. If there is none, you see "There is no signed contract to file a progress report on." (Няма подписан договор, по който да подадете работна карта.) Each click creates a new, separate draft.

If the folders of your main BoQ have responsibles (Отговорник на папка) and you are not a Full-access user, the draft contains only the positions of the folders you are responsible for, and you become its assignee. If you are responsible for no folder, creating fails with "You are not responsible for any folders in this BoQ." (Нямате папки, за които сте отговорник в тази КСС.) The rules are in the section "Folder responsibles and progress reports" below.

How to fill in a progress report

The progress report page works like the draft page of a payment application, without the money.

  1. Click a This period (За периода) cell and type the quantity done since the last progress report. Edits save automatically.
  2. To fill quantities from a measurement sheet, use Import from Excel (Импортирай от Excel); it works as described in Creating and submitting.
  3. Add remarks in the remark column where the office needs an explanation.

The header shows the title Progress report #{n}, the status pill and the Assignee (Отговорник). There is no Total, no money subtotals, no rounds, no export, no Pull from contractor reports and no positions outside the contract. While the progress report is a draft, its assignee can be changed; when your main BoQ uses folder responsibles, only a person with Reports at Full access can change it.

How to submit a progress report

  1. Check the quantities on the draft.
  2. Click Submit (Подай).

The button stays disabled until at least one quantity is above 0. After submitting, the status becomes Submitted (Подадена) and the quantities are locked. The progress report goes to your own office, not to the client. A submitted progress report cannot be withdrawn; if it is wrong, ask the office to return it.

How to accept or return a progress report (office)

Only a person with Reports (Отчети) at Full access (Пълен достъп) sees these buttons, on a submitted progress report.

  1. On the Progress reports page, filter by status Submitted and click Preview (Прегледай) on the progress report.
  2. Check the quantities and remarks.
  3. To accept, click Accept (Приеми) and confirm "Accept this progress report? Accepted progress reports can be used for the next report." The status becomes Accepted (Приета).
  4. To send it back, click Return (Върни). The dialog says "The progress report goes back to its author. Say what needs to be fixed." Type the reason in "What needs to be fixed?" (the comment is required) and click Return. The status becomes Returned (Върната).

How to correct a returned progress report

  1. Open the returned progress report. The office's comment is shown as Reason for return (Причина за връщане).
  2. Click New draft (Нова чернова). A new draft opens with the returned progress report's quantities and remarks.
  3. Correct it and click Submit (Подай) again.

New draft is shown to people with Progress reports at Edit who may edit that progress report: when folder responsibles are in use, its assignee or a Full-access user.

Folder responsibles and progress reports

When at least one folder of your company's main BoQ has a responsible (Отговорник на папка), the same rules apply to progress reports as to payment applications:

ActionProgress reports at Edit, without Full access on ReportsReports at Full access
CreateOnly for the folders you are responsible for (including folders that inherit you from a parent folder). You become the assignee.For the whole contract.
Edit, submit, start a new draftOnly progress reports assigned to you. Others show "Only the responsible person or a manager can edit this report."Any progress report.
Change the assigneeNoYes, while it is a draft
Accept or returnNoYes
See progress reportsAll of them (with View)All of them

The folders a progress report was created for are listed on its page under Folders (Папки). Before any folder has a responsible, nothing is restricted: anyone with Progress reports at Edit files for the whole contract and edits any progress report. How folder responsibles are set is explained in Creating and submitting.

Using accepted progress reports

In a payment application

In the contract's Reports (Отчети) panel, open the menu next to Create report (Създай отчет) and choose New report from progress reports… (Нов отчет от работни карти…). The dialog lists every accepted progress report; the quantities of the ones you tick are added up per position into the new payment application's This period. One progress report can be used in more than one payment application. A progress report that was already used says where, for example "Used in reports #2, #5" („Използвана в отчети №2, №5“). One already in an approved payment application is flagged as a warning, for example "Already in approved report #2" („Вече е в одобрен отчет №2“). If you tick such a progress report and click Create report (Създай отчет), the dialog Progress reports in an approved report (Работни карти в одобрен отчет) first says "Some progress reports have already been used in an approved report. Their quantities will be counted again." and lists the affected ones; click Continue (Продължи) to create the report, or Back (Назад) to change your selection. A payment application built from progress reports shows N progress reports (for example 3 progress reports / 3 работни карти) on its card in the Reports panel and in the title row of its page; click it to see the list (Progress report #1, …) and open any of them. The steps are in Creating and submitting.

In the construction schedule

On the Construction schedule page, the progress source select next to Critical path offers Progress reports (Работни карти: the sum of accepted progress reports) and Latest pay app + progress reports (Последен отчет + работни карти: the latest approved payment application plus the accepted progress reports submitted after it). These two sources are offered only to the contractor company. See Reporting progress.

Common questions

Does the client see my progress reports?

No. Progress reports (Работни карти) are internal to your company. The client sees only the payment applications (Отчети) you submit.

Why can't I see Progress reports in the project sidebar?

The entry appears only in the execution phase, and it is locked without the Progress reports (Работни карти) permission or on the Free plan. Ask your administrator for the permission in your role and in your project access.

Why do I get "There is no signed contract to file a progress report on."?

Your company is not the contractor of a signed contract on its main BoQ in this project. Progress reports are filed by the company doing the work, on its signed contract.

Why does my new progress report contain only some positions?

Your main BoQ uses folder responsibles and you do not have Reports at Full access. The progress report contains only the positions of the folders you are responsible for.

I get "You are not responsible for any folders in this BoQ." What now?

Folder responsibles are in use on your main BoQ and no folder is assigned to you. Ask a person with Reports at Full access to make you responsible for your folders, or to file the progress report.

Why can't I accept a submitted progress report?

Accept and Return need Reports (Отчети) at Full access (Пълен достъп). Progress reports at Edit is not enough.

Can I withdraw a progress report I submitted by mistake?

No. Ask the office to Return it with a comment, then use New draft to correct it.

Does accepting a progress report bill the client?

No. Accepting has no money effect. To bill the client, create a payment application with New report from progress reports… and submit it.

Can I use one progress report in more than one payment application?

Yes. New report from progress reports… offers every accepted progress report, including ones already used. Each used one says which reports it is in, and the Used in column on the Progress reports page lists them all.

Why is a progress report flagged "Already in approved report"?

Its quantities have already been billed in an approved payment application. You can still tick it, but before the report is created you see the warning "Some progress reports have already been used in an approved report. Their quantities will be counted again." Click Continue (Продължи) only if you really mean to bill those quantities again.

Do I need the Reports permission to file progress reports?

No. Progress reports (Работни карти) is its own permission, so site staff can file progress reports without access to payment applications.