Structure: categories, groups, tasks, milestones
On this page
- How to open the structure editor
- The two structure modes
- The elements of a schedule
- How to add categories, group tasks and milestones
- How to put BoQ positions into the schedule
- How to group tasks
- How to move and reorder rows
- How to rename and delete
- Giving a copied schedule its own structure
- Empty group tasks after an MS Project import
- Common questions
- Related
| Where | Construction schedule toolbar → Schedule structure (Структура на графика, gear icon). Opens automatically after New Structure. URL: /projects/{project}/schedule-structure?evaluatedTaskListId=…&scheduleId=…. |
|---|---|
| Who can | Permission Schedule (График) at Edit (Редакция) in your access in this project, to add, move, rename, delete and link. With View (Преглед) the structure page shows View only (Само преглед) and Open the schedule (Отвори графика); you see the structure in the Gantt chart. Paid plan or trial. |
| Related | Creating a schedule, Linking the BoQ: distribution and matching, Gantt view and dependencies, Versions, locking and comparing |
How to open the structure editor
- Open the construction schedule of the BoQ.
- Click Schedule structure (Структура на графика, gear icon) in the toolbar.
- If the current version is Final (Финална), the dialog Edit final version (Редактиране на финална версия) asks "This version is final. Would you like to create a new draft?" Click Create draft (Създай чернова) to continue; structure changes always need a draft.
The button is disabled while you look at an older version from the history. Go to Gantt (Към Гант) takes you back to the timeline.
The two structure modes
| Mode | Created by | What you can do in the structure editor |
|---|---|---|
| Own structure | New Structure, Import from MS Project, or a carry-over of such a schedule | Everything on this page: categories, group tasks, milestones, linking BoQ positions, grouping, moving, renaming, deleting, distribution. |
| Mirror of the BoQ | Copy BOQ Structure, or a carry-over of such a schedule | The categories follow the BoQ automatically. The editor shows every button, but the first change to categories or group tasks (add, rename, move, delete, group, delete the structure) first asks to give the schedule its own structure (below). Milestones, dates and dependencies never ask. |
OUTDATED SCREENSHOT This screenshot is out of date; the text on this page describes the current screen.
Figure: The structure editor of a schedule with its own structure.
- The toolbar: + Category (+ Категория), + Group task (+ Групирана задача), + Add Milestone ◆ (+ Добави етапна цел ◆) and, after selecting rows, Group selected tasks (n) (Групирай избраните задачи).
- The schedule tree: categories, group tasks, tasks and milestones, each with a drag handle on the left.
- Total BOQ coverage (Общо покритие на КСС) shows how much of the BoQ quantity is already placed in the schedule.
- The panel BOQ Structure (preview) (КСС структура (преглед)) shows the BoQ of the same version, with search and Filters (Филтри).
- A drag handle next to a BoQ position or category; drag it onto the left tree to link it.
The elements of a schedule
| Element | What it is | Can contain | Rules |
|---|---|---|---|
| Category (Категория) | A folder bar for a building, floor, stage or trade. Dates and progress are computed from its content. | Sub-categories, group tasks, tasks | The only element that can contain other categories. Cannot be moved into its own sub-tree. |
| Group task (Групирана задача) | One activity that bundles several BoQ positions under a name you choose. | Tasks only | "A group task cannot be placed inside another group task. Ungroup the inner one first." Cannot contain categories or milestones. |
| Task (Задача) | A row linked to a BoQ position or to part of its quantity. Its name is the BoQ description. | — | Rename it in the BoQ, not here. The same position can be placed more than once as long as the distributed quantity does not exceed the BoQ quantity. |
| Merged task (Обединена задача) | One schedule row that stands for a BoQ position split into several instances (for example the same work in several BoQ sections). | Its instances | Editing it applies to all instances below it. |
| Milestone (Етапна цел) ◆ | A key date with no duration. | — | Always a top-level row. Adding it while a category is selected only places it right after that category. |
How to add categories, group tasks and milestones
- To put the new element inside a category, click the category first. Otherwise it is added at the top level (the schedule root).
- Click + Category (+ Категория), + Group task (+ Групирана задача) or + Add Milestone ◆ (+ Добави етапна цел ◆).
- The element appears with a default name: "New Category" (Нова категория), "New group task" (Нова групирана задача) or "New Milestone" (Нова етапна цел). Rename it straight away.
- For a milestone, open Edit milestone (Редактирай етапна цел) and set its name and date.
You can also right-click in the tree. The context menu, section Create (Създаване), offers Create category (Създаване на категория), Create group task (Създаване на групова задача) and, when rows are selected, Group selected tasks (Групиране на избраните задачи). Right-clicking a category creates inside it; right-clicking a task creates in its parent; right-clicking empty space creates at the root.
Success messages: "Category created successfully", "Group task created successfully", "Milestone created successfully".
- The section Create (Създаване) of the context menu.
- Create category (Създаване на категория) adds a category where you clicked.
- Create group task (Създаване на групова задача) adds a group task where you clicked.
How to put BoQ positions into the schedule
- Find the position or category in the BOQ Structure (preview) panel. Use the search bar, or Filters (Филтри) → Include categories (Включи категории) to show only some BoQ categories.
- Drag a position by its handle onto the left tree: onto a category, into a group task, or onto empty space for the root. The message "Task added to the category" (Задачата беше добавена към категорията) confirms it.
- To bring a whole BoQ category, drag the category (tooltip "Drag category into the schedule"). Its hierarchy is rebuilt: the category becomes a category bar, sub-categories become nested bars and each position sits under its bar. Dragging a category always runs as a background job: after the toast "Loading..." (Зареждане...) the progress toast "Updating schedule…" (Обновяване на графика…) appears, and the new bars show in the tree only when the job finishes, with the toast "Updating schedule… - Operation completed". The more positions the category has, the longer this takes.
- To move several at once, tick the checkboxes of positions or categories in the right panel and drag one of them; all selected items move together. Large selections run as a background job.
- Set the distribution of each new row in the left tree. A dropped position arrives with distribution Quantity (Количество) = 0, so it carries no quantity and no value until you choose, for example, Full (Пълно). See Linking the BoQ: distribution and matching.
A position whose quantity is already fully distributed cannot be dragged again; its handle is inactive. The empty tree shows the hint "Drag a task from the BOQ structure on the right to assign it directly, or add a category / milestone from the toolbar."
How to group tasks
From the schedule tree:
- Tick two or more rows in the left tree (checkbox "Select for grouping").
- Click Group selected tasks (n) (Групирай избраните задачи (n)) in the toolbar, or right-click → Group selected tasks.
- A new group task takes the place of the first selected row and holds all selected tasks. Rename it.
From the BoQ panel:
- Tick one or more positions or categories in the BOQ Structure (preview) panel.
- If a category is selected on the left, the hint reads "Group the selected tasks under the selected category"; otherwise "Group the selected tasks at the schedule root".
- Click Group tasks (n) (Групирай задачите). The new group task is named after the first selected BoQ category, if any.
How to move and reorder rows
- Drag a row by its handle ("Move structure row") above or below another row at the same level to reorder it.
- Drop it onto a category bar or a group-task bar to put it inside.
- A category can move into another category, but not into its own sub-tree. A group task cannot be dropped into another group task. A milestone only changes its position in the order and stays at the top level.
- The message "Order updated successfully" (Редът беше обновен успешно) confirms the change.
How to rename and delete
Click the pencil next to a category, group task or milestone (Edit category, Rename group task, Edit milestone). Press Enter or click outside to save, Esc to cancel. Task names come from the BoQ and cannot be edited here.
Use the trash icon to delete. Each deletion asks for confirmation:
| You delete | Confirmation text | Result |
|---|---|---|
| Category (Delete category) | "Are you sure you want to delete the category "{name}"? All subcategories, tasks and milestones in it are deleted too, together with their reported progress." | The whole sub-tree, its dependencies and its progress are removed. |
| Group task | "Are you sure you want to delete the group task "{name}"? The tasks in it are deleted too, together with their reported progress." | The group and its tasks are removed with their progress. |
| Task (Remove task from category) | "Are you sure you want to remove the task "{name}" from the schedule? Its reported progress is deleted. The BOQ item stays." | The link to the BoQ position is removed; the position stays in the BoQ and can be placed again. |
| Milestone (Delete milestone) | "Are you sure you want to delete the milestone "{name}"?" | Only the milestone is removed. |
To delete many rows at once, use Delete whole structure (Изтрий цялата структура) in the toolbar. While rows are ticked, the same button reads Delete selected (n) (Изтрий избраните (n)) and deletes only those rows. n is the number of rows that will be deleted: the ticked rows plus everything inside a ticked category or group task. The button is disabled while the structure is empty. Both ask for confirmation:
- Whole structure: "Are you sure you want to delete the whole schedule structure? All categories, group tasks, milestones and linked BOQ tasks are deleted, together with their reported progress and dependencies. The BOQ stays unchanged."
- Selection: "Are you sure you want to delete the {count} selected rows? Everything inside a selected category or group task is deleted too, together with the reported progress and dependencies. The BOQ stays unchanged."
The delete is all or nothing. When it succeeds, "Deleted {count} rows" appears and the ticks are cleared. If it fails, "An error occurred while deleting the structure" appears, nothing is deleted, and the rows stay ticked so you can try again.
Giving a copied schedule its own structure
A schedule made with Copy BOQ Structure keeps its categories in step with the BoQ. The first time you change its categories or group tasks, the editor asks Edit the structure freely? (Свободна промяна на структурата?): "This schedule was copied from the BOQ, so its categories follow the BOQ. To change them here, the schedule gets its own structure. Everything stays: rows, dates, progress, dependencies and the links to the BOQ. From then on, renaming, adding, moving or deleting a BOQ category no longer changes the schedule; deleted or renamed BOQ items and quantity changes still update it. This cannot be undone."
- Continue (Продължи): the schedule gets its own structure, "The schedule now has its own structure" appears and your change is made. It works like a schedule created with New Structure from then on.
- Cancel (Отказ): "Nothing changed: the categories of this schedule follow the BOQ" appears, and the schedule keeps following the BoQ. The same message appears if the conversion fails.
The question comes once. A locked (Final) version first asks to create a draft. A carry-over to the next BoQ version keeps the schedule's own structure.
Empty group tasks after an MS Project import
An MS Project activity without sub-tasks becomes an empty group task with the badge Needs BOQ tasks (За попълване, tooltip "Empty group — assign BOQ tasks to it"). Click Assign BOQ tasks (Добави позиции от КСС), search with "Search BOQ tasks…" (Търсене на позиции от КСС…), pick the positions, choose the Distribution (Разпределение) and click Assign (Добави). For many activities, let BORO propose the matches. See Linking the BoQ: distribution and matching.
Common questions
Can I change the categories of a schedule copied from the BoQ?
Yes. The first change asks Edit the structure freely? (Свободна промяна на структурата?). Click Continue (Продължи) and the schedule gets its own structure; the change you made then goes through. From then on its categories no longer follow the BoQ.
Why can't I drag a BoQ position into the schedule again?
Its whole quantity is already distributed to schedule rows. Reduce the distribution of an existing row first, then place the rest. See Linking the BoQ: distribution and matching.
Why do I get "A group task cannot be placed inside another group task"?
Group tasks hold tasks only. Ungroup the inner group, or move it into a category instead.
Can I put a milestone inside a category?
No. Milestones are always top-level rows. Selecting a category before adding one only places it right after that category.
How do I start the structure over?
Untick all rows, click Delete whole structure (Изтрий цялата структура) and confirm. Every row, its BoQ links, reported progress and dependencies are removed from the draft; the BoQ itself is not changed. Lock a version first if you may need the old structure again.
Does deleting a task from the schedule delete it from the BoQ?
No. "The BOQ item stays." Only the schedule row and its reported progress are removed.
Why does opening the structure ask me to create a draft?
The current version is locked (Final). Structure changes need a draft; click Create draft (Създай чернова). The locked version stays in the history.
Where do I set dates?
Milestone dates can be set in Edit milestone. All other dates, durations and dependencies are set in the Gantt view. See Gantt view and dependencies.