Partial acceptance

On this page
  1. Why partial acceptance exists
  2. Where you can accept part and where you cannot
  3. How to accept part of the budget (investor)
  4. The draft of the next budget
  5. How to finalize part of a change order
  6. Effects on costs and packages
  7. Common questions
  8. Related
WhereInvestor budget draft: /projects/{project}/drafts/{draft} → Accept part of the budget (Приемане на част от бюджета). Draft of the next budget: Drafts (Чернови) → Draft - budget changes (Чернова - промени по бюджет). Change order: /projects/{project}/change-order-draft/{contract} → Finalize part (Финализирай част).
Who canBudget: an investor company, project permission Execution (Изпълнение) at Edit. Change order: project permission Contract changes (Промени по договор) at Edit. Paid plan or trial.
RelatedChange orders and extensions, Investment budget, Self-managed subcontractors and self-contracts, Contracting schedule and packages

Why partial acceptance exists

A budget or change order can be accepted as a whole only when everything in it is ready. On a real project some positions stay unpriced for weeks, and without an accepted version you cannot sign subcontracts or bill against it. Partial acceptance solves this: you commit what is ready now as a complete, smaller version, and the rest waits in a draft.

The accepted version is a normal, complete version. Contracts, payment applications and the schedule read it like any other version. The left-out positions are not lost; they are carried into a new draft as additions to the next version.

Where you can accept part and where you cannot

DocumentPartial acceptanceButton
Investor's budget draft (first acceptance)YesAccept part of the budget (Приемане на част от бюджета)
Investor's draft of the next budgetYesAccept part of the budget, then Accept selected (Приеми избраните)
Change order for a self-managed subcontractorYesFinalize part (Финализирай част)
Change order on a self-contract (your own contract with a client outside BuildColab)Yes; the draft uses the budget wordingAccept part of the budget, then Accept selected
Change proposed to a contractor or client on BuildColabNo; the other side accepts or declines it in full—
Extension of an existing contractNo; always in full—

How to accept part of the budget (investor)

An investor's budget can be accepted as a whole only when every position has a price. While positions are unpriced, the full acceptance explains: "{count} items still have no price, so the whole budget cannot be accepted. Open the draft and accept only the priced part."

  1. Open the budget draft under Drafts (Чернови).
  2. Click Accept part of the budget (Приемане на част от бюджета) in the action bar. The bill of quantities (BoQ) switches to selection mode, and a bar on top says "Select the items that should become the first version of the budget. The rest moves to a draft of your next budget."
  3. Positions with a price are ticked automatically. Select all priced (Избери всички с цена) restores that selection if you changed it. A position whose price cannot be read is not ticked, so it goes to the next draft rather than into the budget unnoticed.
  4. Adjust the ticks. Ticking a category ticks the positions in it. The bar counts "{count} selected".
  5. Click Budget acceptance (Приемане на бюджет) in the bar. Cancel (Отказ) leaves selection mode without changes.
  6. Confirm the dialog Accept part of the budget: "{selected} of {total} items will become the first version of the budget. The remaining {carried} will be moved to a draft of your next budget, where you can keep working on them." Click Budget acceptance.

The message "Budget accepted. {count} items were moved to a draft of your next budget." confirms it. The project moves to the Execution phase and the accepted budget appears under Budget (Бюджет). The remainder is prepared in the background ("Preparing the draft of the next budget"); until it is ready you may see "Budget accepted. The draft with the remaining {count} items is still being prepared."

Budget draft in selection mode for accepting part of the budget
Figure: Choosing which positions become the first budget version.
  1. The bar title Accept part of the budget (Приемане на част от бюджета) with its explanation.
  2. Ticked positions become the budget; unticked ones move to the next draft.
  3. The counter "{count} selected".
  4. Select all priced (Избери всички с цена) ticks every priced position again.
  5. Budget acceptance (Приемане на бюджет) opens the confirmation.

When the budget acceptance stops

MessageWhy and what to do
"Select at least one item to accept."Nothing is ticked.
"None of the selected items has a price. Tick priced items, or use “Select all priced”."Only unpriced positions are ticked.
"{count} of the selected items have no price and were left out."Unpriced positions you ticked go to the next draft.
Some excluded items are still in use (Част от изключените позиции все още се използват): "These items were left out of the budget, but other documents still refer to them…", listed under Referenced by contracts and Referenced by open inquiriesA left-out position is in a contract or an open offer request. Click Include in the budget (Включи в бюджета) next to a document to tick its positions again, or Include all {count} and accept (Включи всички {count} и приеми) to include them all and accept at once. Or cancel the listed request first.
Some excluded items already have offers (По някои изключени позиции вече има оферти): "Open requests already received offers for these items. You can still leave them out — they move to the next budget, and the offers follow them there."A warning, not a block. Include them with Include in the budget, or click Continue anyway (Продължи въпреки това).

The draft of the next budget

The left-out positions wait under Drafts (Чернови) as Draft - budget changes (Чернова - промени по бюджет): "The lines not yet accepted into the budget. Open the draft to finish and accept them." While it is prepared, the card shows "Being prepared…".

  • Edit, price, import into and version it like the budget draft.
  • Positions already in the budget carry the mark Accepted (Приета): "This line is already accepted into the budget. If you change it, the change goes in with the next acceptance."
  • Click Budget acceptance (Приемане на бюджет) to accept everything: "Every line in this draft will be accepted into the budget as its next version. Continue?"
  • Or click Accept part of the budget, tick lines ("Select the lines to accept into the budget. The rest stay in the draft of the next budget."), click Accept selected (Приеми избраните) and confirm "{selected} of {total} lines will be accepted into the budget as its next version. The remaining {carried} stay in the draft of the next budget…".

Each acceptance creates the next budget version and takes you to the budget. The changes are listed under Budget changes (Промени по бюджет). If the rest could not be prepared: "The selected lines were accepted into the budget, but the draft with the rest was not prepared. Nothing is lost — the remaining lines are kept. Try again in a moment from «Budget changes»."

How to finalize part of a change order

Use this for a change order you finalize yourself, for example for a self-managed subcontractor. A change proposed to another company is always answered in full.

  1. Open the change-order draft: Contract changes (Промени по договор) → Make a change (Направи промяна), or the pill Change draft (Чернова на промяна) in the contract list.
  2. Click Finalize part (Финализирай част) next to Finalize (Финализирай). The draft switches to selection mode with the bar Finalize part of the change (Финализиране на част от промяната): "Tick the changes to commit now — ticking a struck-through row commits its removal. Items already in the contract stay ticked, and everything you leave out moves to a new change draft."
  3. Tick the changes to commit. Added and changed positions are rows you tick; a removed position is a struck-through row, and ticking it commits the removal.
  4. Click Finalize the selected part (Финализирай избраната част). Cancel (Отказ) leaves without changes.
  5. Confirm Finalize part of the change: "{selected} of {total} changes will be committed as a new contract version. The remaining {carried} will move to a new change draft, where you can keep working on them."

The message "Part of the change was finalized. The rest moved to a new change draft." confirms it. The contract gets a new version with only the selected changes. The new draft is prepared in the background ("Preparing the next change draft") and opens by itself when ready. If you open it too early: "The change draft with the remaining items is still being prepared."

Change-order draft in Finalize part selection mode with ticked changes
Figure: Choosing which changes to commit now.
  1. The bar Finalize part of the change (Финализиране на част от промяната) with its explanation.
  2. Ticked changes: an added position and a struck-through removed position (ticking it commits the removal). The changed position above them is left unticked and moves to the new draft.
  3. The counter "{count} selected" ({count} избрани).
  4. Finalize the selected part (Финализирай избраната част) opens the confirmation.

Selection rules and messages

MessageMeaning
"All line items of a removed task must be committed together. Include the whole group, then try again."A removed position with several lines is removed as one group ("{count} line items — removed together").
"This selection commits nothing. Select at least one change."Nothing that changes the contract is ticked.
"{count} of the selected items have no changes to commit — they are already in the contract."Ticked rows that are unchanged are ignored.
"Some selected items are no longer part of this change. The list has been refreshed — check your selection and try again."The draft changed meanwhile.
"A contract extension must be finalized in full. Close this and use Finalize instead."Extensions cannot be split.
"This change cannot be committed in parts. Use Finalize to commit all of it."The draft does not allow a partial commit.
"This draft has no pending changes yet."There is nothing to commit.
"The selected part was finalized, but the draft for the remaining changes could not be started. Nothing is lost — the remaining changes are still on the finalized change order. Open the change orders again in a moment."The new draft is delayed. Reopen Contract changes later.

Effects on costs and packages

  • A budget line carried into a draft that is not accepted yet loses its place in the current budget. Its commitment is shown as Commitment without a live line (Ангажимент без жива позиция): "The budget line was carried into a change order that has not been finalized yet." It returns to its line after acceptance. See Financial dashboard: committed, certified, margin.
  • Positions carried to the next draft stay in their contracting-schedule package, marked moved (пренесена): "A partial budget acceptance carried this line to a new BoQ row; the package follows it here." See Contracting schedule and packages.

Common questions

Why can't I accept the whole budget?

Some positions have no price. Use Accept part of the budget to accept the priced part; the rest moves to the draft of the next budget.

Where did the positions I left out go?

Budget: to Drafts → Draft - budget changes. Change order: to a new change draft, which opens by itself when ready.

Why is "Finalize part" missing?

The change is proposed to another company, which accepts it in full, or it is an extension, which is finalized in full only.

I get "Some excluded items are still in use". What do I do?

A left-out position is in a contract or an open offer request. Include it with Include in the budget or Include all {count} and accept, or cancel the listed request first.

Can I undo a partial acceptance?

No. The accepted part is a new version. Correct it with another change.

Do the offers on a left-out position get lost?

No. When open requests already have offers on it, the position moves to the next budget and the offers follow it there.