Payment applications

On this page
  1. What payment applications are for
  2. Typical sequence
  3. The Reports panel of a contract
  4. Contract corrections (negative lines)
  5. Working with BORO
  6. Pages in this section
  7. Common questions
  8. Related
WherePer contract: the Reports (Отчети) button on the contract's bill of quantities (BoQ) page or on the Contract details page opens the Reports panel. All reports of a project: project sidebar Report Register (Регистър на отчети), /projects/{project}/payment-applications/register. All reports of your company: company sidebar Report Register, /companies/{company}/payment-applications/register. A single report: /projects/{project}/payment-applications/{report}/draft or .../review.
Who canPermission Reports (Отчети): View (Преглед) to open reports and registers, Edit (Редакция) to create, submit, approve, counter, reject, withdraw, record and finalize. Paid plan or trial; not included in the Free plan. You must also be on one side of the contract.
RelatedContracts: signing, details and history, Change orders and extensions, Financial dashboard: committed, certified, margin, End-to-end: from BoQ to payment

What payment applications are for

A payment application (in Bulgarian practice also called „акт“ or „искане за плащане“; in BuildColab always Report / Отчет) records how much of the contracted work was done in a period. It is built on the signed contract: every position of the contract's BoQ is already listed with its contracted quantity and unit price. The company that did the work only enters the quantity for the period. BuildColab multiplies by the contract unit price, keeps the running total, and checks that a fixed-price contract is not billed beyond its quantities.

Every payment application has two sides, taken from the contract:

  • The contractor (изпълнител) is the company that receives the contract and does the work. It creates the report, fills in the quantities, attaches documents and submits it.
  • The client (възложител) is the company that awarded the contract and pays. It reviews the submitted report and approves it, sends a counter-proposal or rejects it.

The paying party sees a payment application only once the subcontractor has submitted it. Drafts do not appear in its lists, registers, exports or BORO answers. A link to a draft opens "This report could not be found. It may have been deleted, or it is not shared with your company. Open it from the register." with the button Open the register (Към регистъра). A report the client records for a self-managed subcontractor is the exception: the client prepares that draft itself, so it sees it.

A general contractor is usually on both sides at once: it is the contractor in its contract with the investor and the client in its contracts with subcontractors. In the registers, reports where you bill your client have the type Budget (Бюджет); reports where a subcontractor bills you have the type Cost (Разход).

When the subcontractor is a self-managed company that does not use BuildColab, the client records and finalizes the report on its behalf. See External payment applications.

Typical sequence

  1. The contract is signed. Reports can only be made on a signed contract. See Contracts: signing, details and history.
  2. Learn how statuses, turns, rounds and cumulative quantities work. See How a payment application works.
  3. Optionally, the site files progress reports (Работни карти) during the period and the office accepts them. They are internal to the contractor. See Progress reports.
  4. The contractor opens the contract's Reports panel and clicks Create report (Създай отчет), or clicks Create report on the project's Report Register (Регистър на отчети) and chooses the contract. It enters the quantities for the period by hand, imports them from Excel, builds them from accepted progress reports or, as a general contractor, pulls them from its subcontractors' approved reports. When folders of the main BoQ have responsibles (Отговорник на папка), each responsible prepares the report for their own folders. It adds remarks and files, picks an assignee and clicks Submit for Approval (Изпрати за одобрение). See Creating and submitting.
  5. If work was done that is not in the contract, the contractor adds it to the report as new positions and prices them. See Positions outside the contract.
  6. The client gets an e-mail and a notification. It reviews the report and clicks Approve (Одобри), Counter (Насрещно предложение) or Reject (Отхвърли). Counter-proposals go back and forth until one side approves or rejects. The side that sent the last proposal can Withdraw (Оттегли) it. See Reviewing, approving, countering, rejecting.
  7. A rejected report can be revised into a new draft. The next period gets a new report.
  8. For a self-managed subcontractor, the client records the report itself and finalizes it in one step. See External payment applications.
  9. Both sides follow all reports in the project or company register, break them down by resource type in the reports summary and export them to Excel. See Register, summary and exports.

The Reports panel of a contract

Reports panel on a contract BoQ with report cards in several statuses and the report history

OUTDATED SCREENSHOT This screenshot is out of date; the text on this page describes the current screen.

Figure: The Reports panel of a contract, opened from the contract's BoQ.

  1. The Related (Свързани) menu in the action bar of the contract's BoQ holds Reports (Отчети), which opens the panel on the right.
  2. The Create report (Създай отчет) button starts a new draft. Only the contractor side sees it, and only on a signed contract.
  3. Each card is one report: Report (Отчет) with its number, the status pill, the total, the creation date and the assignee.
  4. The Your turn (Вашият ред) or Counterparty's turn (Ред на контрагента) badge on a submitted report shows who has to act next.
  5. The Preview (Прегледай) button opens the report.
  6. The Report history (История на отчетите) timeline lists every event: created, sent to the client, new quantities proposed, approved, rejected, withdrawn.

Contract corrections (negative lines)

If a change order lowered a position below what earlier payment applications reported, the next payment application includes a contract correction: a negative line for the difference, under the change order that lowered it. Its value is added to the payment application's total when the report is approved; before that, it is shown as a correction applied on approval.

On the report, the section Contract corrections (Корекции по договор) lists each correction with its negative quantity and amount, tagged with the change order that lowered the position (e.g. Анекс 2), and below them Report lines (Редове на отчета), the corrections and the total. Before approval the corrections row reads Corrections (applied on approval) (Корекции (при одобрение)) and the last row Total after corrections (Общо след корекциите); next to the report's total a red pill shows the same two figures, so the approver sees the value the approval will store. After approval the report's total already includes them, so a report can be worth less than zero; its card in the Reports panel then shows the amount in red with a minus sign.

Working with BORO

The AI assistant BORO can do the same steps for you in chat: list and open reports, create a draft, fill quantities, add positions outside the contract, attach files, set the assignee, submit, counter, approve, reject or withdraw, record and finalize reports for a self-managed subcontractor, and export a report or the reports summary. In the BORO panel, binding steps such as submitting, approving and finalizing are shown to you as an approval card first by default. See What BORO can do.

Pages in this section

  • How a payment application works: the two sides, statuses, turns and rounds, how cumulative quantities and the contract cap work, what approval changes, e-mails and permissions.
  • Creating and submitting: the Reports panel, creating a report, a report from progress reports, folder responsibles and reports for selected folders, entering quantities, Excel import, pulling from subcontractor reports, remarks, files, assignee, submitting, deleting a draft and revising a rejected report.
  • Reviewing, approving, countering, rejecting: the client's review, comparing versions, approving, counter-proposals, rejecting with a reason and withdrawing.
  • Positions outside the contract: billing extra work in a report, pricing it in the resource analysis and how it joins the contract when the report is approved.
  • External payment applications: recording, finalizing and voiding reports for a self-managed subcontractor.
  • Register, summary and exports: the project and company report registers, the reports summary by resource type, and the Excel exports.
  • Progress reports: internal progress reports (Работни карти) from site to office, accepting and returning them, and using them for a payment application or the schedule.

Common questions

Is a "report" the same as a payment application or „акт“?

Yes. BuildColab calls the payment application a Report (Отчет). It is the document the contractor submits for a period under a signed contract, and the client approves it.

Why don't I see the Reports button?

The Reports button needs the Reports (Отчети) permission and a paid plan or trial. The Report Register entry in the project sidebar appears only when the project is in the Execution (Изпълнение) phase. If your role lacks the permission, clicking shows a permission message; ask your company administrator. The investor's budget has no Reports button: an investor does not bill against its budget, but approves the reports on its contracts with subcontractors (from the contract page or the Report Register).

What is the difference between a report and a progress report?

A report (Отчет) is the payment application to the client, with money. A progress report (Работна карта) is an internal record of quantities from site to your office, with no money, never shown to the client. Accepted progress reports can be turned into a report. See Progress reports.

Can I add VAT, retention or an advance deduction to a report?

No. A report contains only quantities and their value at contract prices. VAT, retention and advance live on the contract and are not deducted in reports.

Can I export a report as Обр. 19 or Word?

No. Single reports and the reports summary export to Excel (.xlsx) only.

Does BuildColab issue the invoice after approval?

No. The approval notification says invoicing is next, but invoices and payments are handled outside BuildColab.

My subcontractor says it created a report, but I don't see it. Why?

It is still a draft. The paying party sees a payment application only once the subcontractor has submitted it. Ask the subcontractor to click Submit for Approval (Изпрати за одобрение); you then get an e-mail and a notification, and the report appears in your Reports panel and register.

My subcontractor does not use BuildColab. How do I record its work?

Create it as a self-managed subcontractor and contract it on its behalf. Then use Record report (Запиши отчет) in the contract's Reports panel. See External payment applications.

Why is a report's total lower than the sum of its lines, or below zero?

The report carries contract corrections: a change order lowered positions below what earlier reports had reported, and the difference is a negative line of this report. Its value is added to the total when the report is approved. The section Contract corrections (Корекции по договор) on the report lists them.

In this section

How a payment application works

A payment application (Report / Отчет) claims payment for one period of work under one signed contract. The contractor prepares it as a draft and submits it; the client approves it, counters it or…

Creating and submitting

The contractor creates a payment application (Report / Отчет) from the Reports panel of its signed contract, enters the quantities done in the period, adds remarks and files, and clicks Submit for…

Reviewing, approving, countering, rejecting

When a contractor submits a payment application (Report / Отчет), the client reviews it on the report page and chooses Approve, Counter or Reject. A counter-proposal sends changed quantities back to…

Positions outside the contract

Positions outside the contract are work items that are not in the signed contract but were done and should be paid, for example an extra wall opening ordered on site. The contractor adds them to a…

External payment applications

An external payment application is a report you record yourself for a self-managed subcontractor, a company that does not use BuildColab. You click Record report, enter the quantities from its paper…

Register, summary and exports

The Report Register lists every payment application (Report / Отчет) your company sends or receives, for one project or for the whole company, with filters, grouping and a running total. The Report…

Progress reports

A progress report (Progress report / Работна карта) is an unofficial record of the quantities done on site, filed by site staff for their own office. It looks like a payment application but carries…