Profit, additional costs and totals
On this page
- From resources to the grand total
- Additional costs
- Profit
- Worked example
- How to set additional costs or profit on one position
- How to set the same profit or additional costs on many positions
- How the Report sums several positions
- Where totals appear
- Material and labor split in the export
- Checking for inconsistent prices
- Markup on top of the net total (Надбавка)
- Common questions
- Related
| Where | BoQ editor → Resource analysis (Ресурсен анализ) panel → cost summary (additional costs % and profit %); totals in the grid and the header Total value (Обща стойност). URLs /projects/{project}/drafts/{boq}, /projects/{project}/offers/{boq} |
|---|---|
| Who can | Setting additional costs and profit: project permission Resource analysis (Ресурсен анализ) at Edit (paid plan or trial). Seeing totals: Offers (Оферти) at View. |
| Related | Resource analysis, Working in the BoQ editor, Financial dashboard: committed, certified, margin |
From resources to the grand total
A BoQ price is built bottom-up in seven steps. Each step is recalculated automatically as soon as anything below it changes — a resource, a percentage or a quantity. There is no Recalculate button.
| Step | Number | How it is calculated |
|---|---|---|
| 1 | Value of a resource row (per 1 unit of the position) | Material: price × consumption rate × (1 + DSC% ÷ 100) × AC. Labor: hourly rate × consumption rate × AC. Machinery: daily rate × consumption rate × AC. Service: price × consumption rate × AC. |
| 2 | Direct costs of a type | Sum of the resource values of that type (materials, labor, machinery, services). |
| 3 | Additional costs of a type | Direct costs of the type × the type's additional-cost % ÷ 100. |
| 4 | Total costs | Sum over the four types of (direct costs + additional costs). |
| 5 | Profit | Total costs × profit % ÷ 100. |
| 6 | Unit price | Total costs + profit, rounded to cents (2 decimals). |
| 7 | Position value | Unit price × quantity, rounded to 2 decimals. |
| — | Category total | Sum of the values of every position in the category and all its subcategories. |
| — | Grand total (Total value) | Sum of all position values in the version. |
Internally BuildColab stores money with three extra decimal places, so intermediate results are not rounded too early; resource values are shown with 3 decimals, prices and totals with 2. Money is shown in the project currency (EUR).
Additional costs
Additional costs (Bulgarian допълнителни разходи) are the overheads you add on top of direct costs — site overheads, general company costs and similar. In the resource analysis they are set as a separate percentage for each resource type: one % for materials, one for labor, one for machinery, one for services. Each percentage applies only to the direct costs of its own type. For example, 50% on labor does not change the material cost.
Delivery and storage costs (DSC %, Bulgarian ДСР %) are different: they are entered per material row and are already included in that row's value (step 1). The additional coefficient (AC, ДК) is a multiplier per resource row, also in step 1.
There is no fixed-amount additional cost in the resource analysis. If you need a fixed amount per unit, add it as a service row.
Profit
Profit (печалба) is a percentage of the total costs of the analysis (step 5), set in the Profit: row of the cost summary. It can be any value of 0 or more, with up to 4 decimals. A direct price typed into the grid has no profit: it becomes a single "Unit price" line with 0% profit.
Worked example
Position "Ceramic floor tiles on adhesive", quantity 120 m², priced with this resource analysis for 1 m²:
| Resource | Type | Consumption rate | Price (EUR) | DSC % | AC | Value per m² (EUR) |
|---|---|---|---|---|---|---|
| Ceramic tiles | Material | 1.05 m² | 20.00 | 3 | 1.00 | 1.05 × 20.00 × 1.03 × 1.00 = 21.63 |
| Tiler | Labour | 0.6 m.h. | 15.00 | — | 1.1 | 0.6 × 15.00 × 1.1 = 9.90 |
Additional costs: materials 0%, labor 50%. Profit: 10%.
| Type | Direct costs | Add. costs % | Add. costs value | Total |
|---|---|---|---|---|
| Materials | 21.63 | 0 | 0.00 | 21.63 |
| Labour | 9.90 | 50 | 4.95 | 14.85 |
| Machinery | 0.00 | 0 | 0.00 | 0.00 |
| Services | 0.00 | 0 | 0.00 | 0.00 |
| Total | 31.53 | 4.95 | 36.48 |
- Profit = 36.48 × 10% = 3.648.
- Unit price = 36.48 + 3.648 = 40.128, rounded to 40.13 EUR per m².
- Position value = 40.13 × 120 = 4,815.60 EUR.
- If the category "Floors" also contains "Skirting" with a value of 1,184.40 EUR, the category total is 4,815.60 + 1,184.40 = 6,000.00 EUR.
- If the BoQ has one more category "Walls" with 14,000.00 EUR, the BoQ grand total is 20,000.00 EUR.
If you now raise the labor additional costs to 60%, labor add. costs become 5.94, total costs 37.47, profit 3.747, unit price 41.22 EUR, and the position value 4,946.40 EUR — the category and grand totals follow immediately.
- The Direct costs (Преки разходи) column: the sum of each type's resource values.
- The Add. costs % field of each type, editable.
- The Add. costs Value: direct costs × %.
- The Total row: total costs of the analysis.
- The Profit: row with the profit % and the profit value.
- The resulting unit price per unit of measure.
How to set additional costs or profit on one position
- In the BoQ editor, tick the position. The Resource analysis panel opens.
- In the cost summary, click the % field of the type row (for additional costs) or of the Profit: row.
- Type the percentage and press Enter or ✓. Esc or ✗ cancels.
The change applies to the shared analysis, so all identical positions in the BoQ (same description, unit and note) get the new unit price. If the BoQ version is locked, confirm the New version warning first.
How to set the same profit or additional costs on many positions
- In the BoQ editor, tick several positions, a category, or all top-level categories to cover the whole BoQ. The panel becomes Report (Справка).
- In the Report's cost summary, type the profit % or an additional-cost % and press Enter or ✓.
BORO can do the same for a whole BoQ in one step ("set 12% profit on this BoQ"). In the BORO panel the change waits for your approval by default; over MCP no approval is asked.
How the Report sums several positions
The Report of several positions weights every analysis by its position's quantity:
- direct costs per type = Σ (direct cost per unit × position quantity);
- resources are grouped by library item; Qty = Σ (consumption rate × position quantity);
- rates and AC are quantity-weighted averages;
- the additional-cost % shown is the effective weighted percentage; profit % = Σ profit ÷ Σ costs;
- the last column shows the summed total, labeled "summed".
- The ticked category in the grid selects all positions under it.
- The panel title Report (Справка) with the number of selected work items and their Total value.
- The weighted cost summary; a % saved here is set on every selected analysis.
- The Qty (К-во) column: consumption rate × position quantity, added up.
Where totals appear
| Place | What it shows |
|---|---|
| BoQ editor header — Total value | Grand total of the version on screen (hidden on quantity-only BoQs). |
| Header summary bar — Summary · {count} tasks / Total value | Count and value of only the positions that match the active filter categories. |
| Category row | Total of the category subtree. |
| Resource analysis position card | Unit price and Total value (unit price × quantity). |
| Report header | Sum of the selected positions' values. |
| Draft and offer cards — Total value | Grand total of the current version. |
| History panel — Total value per version | The total stored when that version was locked. |
| Budget grid — Committed, Certified, Margin | Per budget line: committed = signed subcontract quantity × price; certified = approved in subcontractors' payment applications; margin = budget − committed, and margin % = margin ÷ budget, to 1 decimal. See Financial dashboard: committed, certified, margin. |
Material and labor split in the export
The Excel export can show separate material and labor unit prices (Split (material / labour)). The material unit price is the unit price × (material resources ÷ total costs of the analysis); the labor unit price is the rest of the unit price. Each row total is quantity × (material + labor). See Exporting.
Checking for inconsistent prices
The same work should have one price in a BoQ. Within one BoQ, positions with the same description, unit and note share one analysis, so they cannot differ. Positions that differ only in their note (for example "Floor 1" and "Floor 2") can have different prices. When importing, rows with the same description, unit and note but different prices are reported as unit-price conflicts and must be resolved before saving. BORO can list positions in a BoQ where the same work (description and unit) is priced differently.
Markup on top of the net total (Надбавка)
A markup (Bulgarian надбавка, for example "Главно ръководство ГИ – 5%") is a percentage the main contractor charges on top of the net value of selected work in a bill of quantities (BoQ). Unit prices, position values, category totals and the net BoQ value do not change: the markup is calculated from them. A document has at most one markup. Nothing about the markup is shown under the BoQ grid; its summary lives in the GC markup (Надбавка ГИ) panel. Printed documents and Excel exports keep the markup lines at the bottom.
The markup is a term of the contract between the client (investor) and the general contractor (GC). The client marks such a contract with the switch General contractor (with a management markup) (Главен изпълнител (с надбавка за управление)) and sets the % in the contract's draft terms (or in Contract with a contractor (Сключи договор с изпълнител)); after signing it changes only through a change order, edited by the client. The GC sees it read-only, marked Set by the client (Зададена от възложителя). An offer request carries only the switch, never a %: it tells the GC candidates that the contract will carry a markup. An investment budget has no markup of its own, because it also holds costs the GC does not manage; it shows the markup of its GC contracts instead (see "The markup on the budget" below).
Where: the GC markup (Надбавка ГИ) action in the BoQ action bar opens and closes the panel on the right. It is there on a contract with the GC (also while it is a draft), its change-order drafts and the budget, and only where there is a markup to show: a contract without the switch, an offer, an offer request and a budget draft have none. The panel is closed when you open a BoQ and opens only when you click the action.
How to add a markup
- As the client, open the draft contract with the GC (or a change-order draft on it) and click GC markup (Надбавка ГИ) in the action bar, or use the GC markup card in the contract terms. The panel opens. The contract must have General contractor (with a management markup) (Главен изпълнител (с надбавка за управление)) switched on.
- Click Add markup (Добави надбавка). The panel shows the settings.
- Check the Name (Наименование) and type the Default % (% по подразбиране). The default % applies to every category and position without a % of its own.
- Click Add markup (Добави надбавка). The % GC (% ГИ) and With markup (С надбавка) columns appear in the BoQ, and the header shows the total with markup.
The markup view options
The View (Изглед) card at the top of the GC markup panel holds four independent options. BuildColab remembers them in your browser separately for budgets, contracts, change-order drafts and payment applications.
- % GC (% ГИ): show or hide the column with the markup % of each category and position.
- With markup (С надбавка): show or hide the column with each row's value including the markup.
- Prices (Цени): Net (Нетни) or With markup (С надбавка). With markup, the Unit price and Value columns show the amounts × (1 + %). Prices can then not be typed in the grid: switch back to Net to edit a price. The unit price with markup is rounded per unit, while the value is the net value × (1 + %), so quantity × unit price can differ by a few cents. In this mode the With markup column shows Net (Нетно) instead, so both values stay visible.
- Scope (Обхват): All (Всички), In scope (В обхват, a % above 0) or Out of scope (Извън обхват, 0%). The BoQ shows only the matching positions and the categories that contain them.
How to set a different markup % on a category or a position
- In the % GC (% ГИ) column, click the % of the category or position. A small window opens.
- Choose Inherit (Наследи; the inherited % is shown in brackets), Own % (Собствен процент) and type it, or Out of scope (Извън обхвата, 0%).
- For a category you can also tick Clear the explicit % of the subcategories and positions beneath (Изчисти изричните проценти в подкатегориите и позициите), so everything below inherits again.
- Click Save (Запази). Cancel (Отказ) or Esc closes without a change.
Markup % rules: an inherited % takes the nearest parent category that has its own %, or the default %. 0 leaves the category or position out of scope: it is not part of the markup base. The % is between 0 and 100, with up to 2 decimals. In the % GC column an own % is a filled orange chip, an inherited % a grey dashed chip, and out of scope reads "0% · out" (0% · извън). A position that appears in several categories is counted per category.
The GC markup panel
Under the view options the panel shows one card per % (the markup amount and the net value it is calculated on), the out-of-scope value, Total works (net) (Общо СМР (нетно)), Total markup (Общо надбавка) and Total with markup (Общо с надбавка). Each markup amount is rounded to the cent. On a contract the last line is Contract value (Стойност на договора), followed by Earned to date (Спечелена до момента) with a progress bar — the markup of the approved payment applications so far — and Who sees it (Кой вижда): the client and the general contractor see the same amount, subcontractors and their offers see only net values.
With a markup, the header of the BoQ shows Total value (with markup) (Обща стойност (с надбавка)) instead of Total value. Hover over the amount to see the net total, the markup per % and the total with markup. Without a markup the header shows the net Total value as before.
The markup on the budget
The budget has no markup of its own and nobody edits a markup there. Its GC markup panel is read-only: the view options GC markup (by contract) (Надбавка ГИ (по договори)) and Certified markup (by contract) (Сертифицирана надбавка (по договори)) show or hide two columns with the markup contracted on each budget line by its GC contract, and what approved payment applications certified of it. Only your company, as the budget's owner, sees these figures. A line with no GC contract shows nothing; a category shows the sum of its positions once they are loaded. The budget's Total value (Обща стойност) stays net; hover over it to read "+ GC markup contracted on top (by contract): …". Below, the panel lists each GC contract on the budget's lines with its Contracted markup (Договорена надбавка) and Certified to date (Сертифицирана до момента), then the totals. If no GC contract carries a markup, the panel says "No GC contract on these lines carries a markup."
Markup settings
Click Settings (Настройки) in the panel header. Besides the name and the default %:
- By label (По етикет): type a % next to one or more BoQ labels and click Apply by labels (Приложи по етикети). Every position with that label gets the %; an empty field leaves the label alone.
- Tick categories in the BoQ first. Selected in the BoQ (Избрани в КСС) then shows how many: type a % and click Set (Задай), or click Clear (Изчисти) next to Clear the own % under the selected categories (Изчисти собствените % под избраните категории). The categories stay ticked.
- Scope suggestion (Предложение за обхват): when some positions are already subcontracted, the panel says how many are subcontracted and how many are own forces; Apply: own forces → 0% (Приложи: собствени сили → 0%) takes the own-forces positions out of scope.
- Last change (Последна промяна) names who changed what and when; history (история) lists the earlier changes, newest first, 50 at a time; Show earlier changes (Покажи по-ранни промени) loads the next ones.
Save (Запази) stores the name and the default %; Cancel (Отказ) returns to the overview.
Removing a markup, and when it cannot be changed
In Settings click Remove markup (Премахни надбавката) and confirm. The markup and every % set on categories and positions are removed; net prices are not affected. The markup of a signed contract is locked: the panel shows "Panel · locked" (Панел · заключено), the % cannot be changed, and Propose a change with an annex (Предложи промяна с анекс) opens the contract's change orders. An older BoQ version opened from History is read-only too.
The switch set on an offer request goes to the GC offers that answer it and to the contract made from the awarded offer; the % is then set in that contract's draft terms. A contract made with Contract with a contractor (Сключи договор с изпълнител) takes the switch and the % from the dialog. A change order copies its contract's switch and markup. Budgets, offers, contracts with subcontractors and subcontractor offers carry none: subcontractors never see it.
Common questions
Why is my unit price a few cents different from my own calculation?
BuildColab keeps three extra decimals in intermediate steps and rounds only the unit price to cents and the value to 2 decimals. A calculation that rounds each step will drift by a cent or two.
Are additional costs applied before or after profit?
Before. Additional costs are added to the direct costs of each type; profit is then calculated on the total of direct and additional costs.
Does the additional-cost % for labor also apply to materials?
No. Each type has its own percentage, applied only to that type's direct costs.
Why does a direct price ignore my profit?
A typed unit price replaces the analysis with one "Unit price" line with 0% profit. If you want profit on top, build a resource analysis instead.
How do I set the same profit for the whole BoQ?
Tick all top-level categories, then type the profit % in the Report and save. This overwrites the profit of every analysis in the selection. Or ask BORO.
Why did the total change when I only changed one position?
Identical positions share one analysis. Changing its price changes every position that uses it, and all their category totals.
Does the BoQ total include VAT?
No VAT is added by the BoQ. The totals are the sums of quantity × unit price as entered.
Why does the filtered total differ from the grand total?
While filter categories are applied, the summary bar shows only the matching positions. Clear the filter in Controls to see the whole BoQ again.
Does a markup change my unit prices?
No. The stored unit prices and values stay net; the markup is calculated from them. You can choose to display prices with markup (Prices → With markup in the GC markup panel), but that only changes what the grid shows.
Why can't I change the markup?
Only the client sets it: in the terms of a contract with the GC before it is proposed, and in a change order after signing. For the GC the panel and the contract terms show it read-only, marked Set by the client (Зададена от възложителя). A budget has no markup of its own to change.