Budget, costs and reports

On this page
  1. How the money fits together
  2. Typical sequence
  3. Pages in this section
  4. Common questions
  5. Related
WhereProject sidebar, Execution phase: Budget (Бюджет) or Contract with client (Договор с възложител), Contracts with contractors (Договори с изпълнители), Financial dashboard (Финансово табло); the construction schedule toolbar → Reports (Справки).
Who canProject permissions Execution (Изпълнение), Financial dashboard (Финансово табло), Reports (Отчети) and Schedule (График), each at View (Преглед) or higher. An investor's Budget (Бюджет) and the financial dashboard also need Budget preparation (Изготвяне на бюджет). Paid plans or trial; none of these is in the Free plan.
RelatedPayment applications, Contracts and changes, Schedule, The project page

How the money fits together

ScreenSideQuestion it answers
Investment budget — Budget / Contract with clientIncomeWhat will we be paid, line by line? How much is already approved?
Costs — Contracts with contractorsCostsWhat did we contract to subcontractors, and how much have they claimed?
Financial dashboard: committed, certified, marginBothFor each budget line: budget against committed costs, executed and remaining on both sides.
Reports and Cash flowPlanHow much work and which resources do we plan for each week, month, quarter or year?
Contract finance: certificates, invoices and payments — company sidebar → Contract financeMoneyWhich certificates of acceptance and payment are confirmed, what is invoiced, paid, due or overdue, and how much advance and warranty deductions are held per contract?

Three figures connect income and costs on every budget line: Committed (Ангажимент) — what you signed with subcontractors; Certified (Сертифицирано) — what of it they claimed in approved payment applications; and Margin (Марж) — budget minus committed. All money is in EUR.

Key figures on the project page of a project in execution
Figure: The finance figures on the project page of a contractor.
  1. The Budget or Contract with client tile with Reported (Отчетено): the income side.
  2. The Contracts with contractors tile: the cost side. Here the contractor has no subcontracts yet, so it shows "0 contracts".
  3. The Certified this month tile with the link to the financial dashboard.

Typical sequence

  1. Get a budget. As an investor, accept a budget draft; as a contractor, sign the contract with your client. The project moves to Execution and the budget page appears. See Investment budget.
  2. Contract the work. Award parts of the budget to subcontractors through offer requests and contracts. Every signed line becomes a commitment. See Costs.
  3. Watch the margin. Switch on the cost columns in the budget, or open the financial dashboard, to compare budget and costs and link any unlinked contract lines. See Financial dashboard: committed, certified, margin.
  4. Bill and approve. As a contractor, submit payment applications against your contract with client; approve your subcontractors' payment applications. An investor does not bill against its budget: progress is reported on the contracts with subcontractors. See Payment applications.
  5. Invoice and get paid. If your company includes the contract in Contract finance (Финанси по договори), every approved payment application creates a certificate of acceptance and payment in your register. Confirm it, register the invoices and payments against it and release the warranty deductions. See Contract finance: certificates, invoices and payments.
  6. Plan the cash flow. From the construction schedule, open Reports for the cash flow and the resources by period. See Reports and Cash flow.

Pages in this section

  • Investment budget — the budget or contract with the client, its action bar, the committed/certified/margin columns and how the budget changes.
  • Costs — the list of contracts with subcontractors, a contract's page, its payment applications and change orders.
  • Financial dashboard: committed, certified, margin — the definitions and formulas, every column of the dashboard, and linking unlinked contract lines.
  • Reports — the Reports screen with every report kind, filters, grouping, scales and Excel export.
  • Cash flow — the planned value of work by period, with a worked example.
  • Contract finance: certificates, invoices and payments — including a contract in finance, certificates of acceptance and payment, invoices, payments, the advance, warranty deductions, reports, financial terms and settings.

Common questions

Why don't I see any of these screens?

They appear in the Execution phase only and need a paid plan and the matching permissions. Accept your budget or sign your contract first.

What is the difference between "Reports" (Справки) and "Reports" (Отчети)?

Справки are the planned cost and resource reports opened from the schedule. Отчети are payment applications, opened with Reports in a contract's action bar (a contract with a subcontractor or the Contract with client; the investor's budget has none) and listed in the Report Register.

Can I see a profit-and-loss of the project?

The financial dashboard and the margin column show budget against committed costs per line and in total. Your overheads outside the project are not part of BuildColab.

Where do I record invoices and payments for a contract?

In Contract finance (Финанси по договори) in the company sidebar, after your company has included the contract in finance. See Contract finance: certificates, invoices and payments.

In this section

Investment budget

The budget page shows the project's accepted, read-only bill of quantities (BoQ) on the income side: for an investor it is the Budget, the investment budget accepted from a budget draft; for a…

Costs

The Contracts with contractors page is the cost side of a project: every signed contract your company awarded to a subcontractor, with its current value and how much of it has been reported in…

Financial dashboard: committed, certified, margin

The Financial dashboard compares, line by line, the project budget (what you will be paid) with your costs (what you contracted to subcontractors), and shows how much of each side is already approved…

Reports

The Reports screen spreads the priced bill of quantities (BoQ) over time according to the construction schedule. It shows, by week, month, quarter or year, the planned cash flow and the planned…

Cash flow

The cash flow report shows how the planned value of the work is spread over time: how much work, in euros, the schedule plans for each week, month, quarter or year. Value = planned quantity in the…

Contract finance: certificates, invoices and payments

Contract finance is your company's internal register of the money on a contract. Approved payment applications on an included contract are put into a Certificate of acceptance and payment, one report…