Reporting progress
On this page
| Where | Construction schedule → table column % Done (Изп. %). URL: /projects/{project}/schedule. |
|---|---|
| Who can | Typing progress: permission Schedule (График) at Edit (Редакция). With View (Преглед) the column is visible but your entries are refused. Choosing the progress source: anyone who can open the schedule. The sources Progress reports and Latest pay app + progress reports are offered only to the contractor company of the contract. Paid plan or trial. |
| Related | Gantt view and dependencies, Versions, locking and comparing, Publishing to subcontractors (slices), Linking the BoQ: distribution and matching |
How progress works
- Percent, not quantity. You always enter a whole percent from 0 to 100. There is no field for an executed quantity; the executed quantity is calculated as planned quantity × percent.
- Append-only. Every entry is a new record with its date and reporter. The table shows the latest value; earlier values stay in the journal.
- Independent of versions. Locking freezes the plan, not the actuals. You can report progress on a Final version without creating a draft.
- Latest entry wins. If you report on a group task and later on one of its tasks, the later entry counts for that task.
Everything above describes the progress source Schedule progress (Прогрес от графика), the default. The next section explains the computed sources.
Where progress comes from: the progress source
The select next to Critical path (Критичен път) in the header of the Construction schedule page chooses where the percent of every row comes from. Its accessible name is Progress source (Източник на прогреса). It exists so that the schedule can show what was actually certified or recorded on site, without anyone retyping percents.
| Source (EN / BG) | Executed quantity of a BoQ position |
|---|---|
| Schedule progress / Прогрес от графика | The default. The latest percent typed in % Done × the planned quantity, as described above. |
| Approved pay apps / Одобрени отчети | The sum of the quantities of all approved payment applications (Отчети) on the position. |
| Progress reports / Работни карти | The sum of the quantities of all accepted progress reports (Работни карти) on the position. |
| Latest pay app + progress reports / Последен отчет + работни карти | The executed-to-date quantity of the latest approved payment application that has a quantity on the position, plus the accepted progress reports on that position submitted after that payment application was approved. Use it to see certified work plus what the site has recorded since. |
Rules of the three computed sources:
- Percent = executed ÷ contracted quantity of the position, capped at 100 %. A position split over several schedule rows gives every row the same percent.
- % Done is read-only. You cannot type progress; hovering the cell shows "Progress is calculated from the reports" (Прогресът се изчислява от отчетите). Switch back to Schedule progress to type again.
- Nothing is written. The computed percents are not added to the progress journal. Your typed entries stay untouched and come back when you switch to Schedule progress.
- Categories and group tasks are weighted by value: an expensive task counts more than a cheap one. In Schedule progress categories stay an equal average.
- Executed Qty (Изп. количество) shows the real quantity from the reports, and Executed Value and the remaining columns follow from it.
- The schedule refreshes by itself when a payment application or progress report changes.
How to change the progress source
- Open the project and click Construction schedule (Строителен график) in the project sidebar.
- In the header, next to Critical path (Критичен път), open the progress source select. It shows the current source, Schedule progress by default.
- Choose Approved pay apps, Progress reports or Latest pay app + progress reports. The bars, the % Done column, the value columns and Overall progress recalculate.
Your choice is remembered for you and this project in this browser; other people keep their own choice. Changing the source changes only what you see, never the data.
When a source is greyed out
The computed sources need the schedule to be built on your company's main bill of quantities (BoQ), the one your payment applications run on, with a signed contract. When a source cannot be used, it is greyed out in the select and hovering the select shows the reason:
| Message (EN) | Message (BG) | Meaning |
|---|---|---|
| The schedule is not on a BoQ with a contract | Графикът не е върху КСС с договор | The schedule's BoQ has no signed contract, so there are no payment applications to count. |
| The schedule is not on the main BoQ | Графикът не е върху основната КСС | The schedule is built on another BoQ, for example an offer, not on the main BoQ the payment applications run on. |
| Progress reports are internal to the contractor | Работните карти са вътрешни за изпълнителя | Your company is the client side of the contract. Progress reports belong to the contractor and are never shown to the client, so only Approved pay apps is offered. |
| Not available yet | Все още не е налично | Any other reason the source cannot be used for this schedule. |
If a remembered source is no longer available, the schedule falls back to Schedule progress.
Overall progress
Above the Gantt table the Construction schedule page shows Overall progress (Общо изпълнено) with a percent and a bar. It is the average progress of the top-level categories, weighted by each category's planned value; if any top-level category has no price, every category counts equally. Categories without progress yet are left out, and the line is hidden until at least one category has progress. It follows the selected progress source.
Which rows take progress
| Row | Can you enter % Done? | What happens |
|---|---|---|
| Task linked to a bill of quantities (BoQ) position | Yes | The value is stored for the task. |
| Group task (Групирана задача) | Yes | The same percent is given to every task inside the group. |
| Merged task (Обединена задача) | Yes | The same percent is given to each instance below it. |
| Category (Категория) | No | Computed from the rows inside as an equal (unweighted) average of their latest percents. In a computed progress source the average is weighted by value. |
| Milestone (Етапна цел) | No | — |
Category values are recalculated in the background right after each entry, so they may update a moment later than the task you changed.
How to report progress
- Open the construction schedule. If % Done (Изп. %) is not visible, click Columns (Колони) and move it out of Hidden.
- Click the % Done cell of the task. It becomes an input with the placeholder "0–100".
- Type a whole number from 0 to 100.
- Press Enter, click the checkmark, or click outside the cell to save. Esc or the cross cancels.
- The toast "Progress updated successfully" (Изпълнението беше обновено успешно) confirms the entry. A decimal, an empty value or a number outside 0–100 is never saved and never rounded or capped to 100. As soon as you type a number above 100, the cell shows "Progress cannot be more than 100%" (Изпълнението не може да е повече от 100%). With Enter or the checkmark, the cell stays open and shows that message, or "Invalid percentage (0–100)" (Невалиден процент (0–100)) for a decimal or an empty value, so you can correct it. If you click outside the cell instead, the entry is discarded without a message and the cell shows the previous percent again.
OUTDATED SCREENSHOT This screenshot is out of date; the text on this page describes the current screen.
Figure: Reporting progress in the Gantt table.
- The % Done (Изп. %) cell in edit mode.
- The checkmark saves the value; the cross cancels.
- The filled part of the bar shows the reported progress.
- Executed Value and Remaining Value recalculate from the percent.
What progress drives
| Column or element | Calculation |
|---|---|
| Executed Qty (Изп. количество) | Planned Qty × % Done |
| Executed Value (Изп. стойност) | Planned Value × % Done |
| Remaining Qty (Остатъчно количество) | Planned Qty − Executed Qty |
| Remaining Value (Остатъчна стойност) | Planned Value − Executed Value |
| Bar on the timeline | Filled from the left in proportion to % Done (legend Progress, Напредък) |
| Group task values | Sum of the value columns of the tasks inside it |
OUTDATED SCREENSHOT This screenshot is out of date; the text on this page describes the current screen.
Figure: Progress rolled up to a category, with the executed and remaining columns.
- A category row: its % Done is computed from the rows inside and cannot be typed.
- Task rows with their reported % Done.
- Executed Value (Изп. стойност) and Remaining Value (Остатъчна стойност) calculated from the percent.
Rows with distribution Manual, rows without a priced BoQ position and milestones show no quantity or value. Progress typed in the schedule does not create a payment application; payment applications have their own quantities. The other direction works through the progress source: approved payment applications and accepted progress reports can drive the schedule. See Payment applications.
When the BoQ quantity changes
- Distribution Full: the percent is rescaled so the executed amount stays the same. Example: 50 % of 15 m³ becomes 25 % after the quantity grows to 30 m³.
- Distribution Percent or Quantity: the percent is not changed. You see "Some schedule tasks must be redistributed manually after the quantity change." Adjust those rows in the structure editor.
- Distribution Manual: nothing changes.
See Linking the BoQ: distribution and matching.
Progress history
The table shows only the latest percent of each task; there is no history screen. To see the full journal of a task — every entry with its date, who reported it and the note — ask BORO, for example "When did the slab formwork reach 50 % and who reported it?" BORO can also record progress for you, with an optional note; in the BORO panel the entry goes through an approval card by default. See What BORO can do.
Progress on a subcontractor slice
A subcontractor sees a read-only slice of the main contractor's master schedule, but it can still report % Done on its tasks there, the same way. See Publishing to subcontractors (slices).
Common questions
Can I report an executed quantity instead of a percent?
No. The schedule accepts only a whole percent. The executed quantity is calculated from it. If you know the quantity, divide it by the planned quantity of the row.
Why can't I type progress on a category?
Category progress is computed as the average of the rows inside it. Report on its tasks or group tasks.
Do I need to create a new draft to report progress on a locked schedule?
No. Progress works directly on a Final version and does not create a new version.
Why does the category value update a moment later?
The roll-up runs in the background right after your entry. Wait a moment; the page refreshes by itself.
I typed 45.5 and got "Invalid percentage (0–100)". Why?
Only whole numbers are accepted. Type 45 or 46.
I typed 120 and the cell went back to the old percent. Was it saved as 100?
No. A value above 100 is refused, not capped. The cell said "Progress cannot be more than 100%" while you typed; clicking outside the cell then discards the entry and shows the previous percent again. Type a whole number from 0 to 100 and press Enter.
Can I see who reported a value?
Yes, through BORO: ask for the progress history of the task. It lists every entry with date, reporter and note.
Why can't I type in % Done any more?
The progress source is set to a computed source (Approved pay apps, Progress reports or Latest pay app + progress reports). The cell shows "Progress is calculated from the reports". Switch the select next to Critical path back to Schedule progress.
Can the schedule take progress from approved payment applications?
Yes. Choose Approved pay apps in the progress source select next to Critical path on the Construction schedule page. Each position's percent becomes the approved quantity ÷ the contracted quantity, capped at 100 %. The schedule must be on your main BoQ with a signed contract.
Why are Progress reports and Latest pay app + progress reports greyed out?
Either the schedule is not on your main BoQ with a signed contract, or your company is the client side of the contract: "Progress reports are internal to the contractor". Progress reports belong to the contractor, and the client never sees them.
If I switch to Approved pay apps, are my typed percents lost?
No. Computed progress sources never write to the progress journal. Switch back to Schedule progress and your typed values are there again.
Does my choice of progress source change what my colleagues see?
No. The choice is remembered per person and project in your browser. Each person picks their own.