BoQ documents and versions list

On this page
  1. Kinds of BoQ document
  2. When the Drafts page is shown
  3. The draft card
  4. How to create a new budget draft
  5. The card menu
  6. Version history of a draft
  7. Accepting a budget draft
  8. The "Draft - budget changes" card
  9. Other places where BoQs are listed
  10. Common questions
  11. Related
WhereProject sidebar → Drafts (Чернови), or the Drafts card on the project page. URL /projects/{project}/drafts
Who canInvestor company on the project. Viewing needs project permissions Budget preparation (Изготвяне на бюджет) and Offers (Оферти) at View. Creating, renaming, duplicating and deleting need Offers at Edit. Accepting the budget needs Execution (Изпълнение) at Edit. Budget drafts need a paid plan.
RelatedWorking in the BoQ editor, Versions, comparing and locking, Partial acceptance, Investment budget

Kinds of BoQ document

Every BoQ in BuildColab is a document of a certain kind. The kind decides where the BoQ is listed and whether you can edit it directly.

KindWho has itWhere it is listedEditable?
Budget draftInvestor, budgeting phaseDrafts (Чернови)Yes, until it is accepted
Investment budget (accepted budget)Investor, execution phaseBudget (Бюджет)No. Changes go through a change order.
OfferContractor or subcontractorOffers (Оферти)Yes, until it is contracted
Offer request base (quantity bill)The company that sends an offer requestOffer requestsQuantities only, no prices
Contract BoQBoth parties of a signed contractBudget / contracts pagesNo. Changes go through a change order.
Draft of the next budget (budget changes)Investor, after a partial acceptanceDrafts, as the card Draft - budget changesYes

A new BoQ created while your company is in the budgeting phase of the project is a budget draft. A new BoQ created in any other phase is an offer.

When the Drafts page is shown

The Drafts (Чернови) entry in the project sidebar is shown only when all of these hold:

  • your company is the investor on the project;
  • the project is in the budgeting phase for your company, or in execution while a draft of the next budget is still open;
  • your role has Budget preparation (Изготвяне на бюджет). The page itself also checks Offers (Оферти), so in practice you need both permissions.

What the Drafts page shows depends on the phase:

SituationWhat you see
Budgeting phaseOne card per budget draft, oldest first, followed by a + card for a new draft. With no drafts yet, only the + card is shown.
Execution phase, no open draftThe text No open drafts (Няма отворени чернови).
Execution phase, a draft of the next budget existsOne card Draft - budget changes (Чернова - промени по бюджет). There is no + card, because new drafts make no sense once the budget is accepted.
The project could not be loadedError (Грешка).

The draft card

Each budget draft on the Drafts page is a card with these elements:

ElementEN labelBG labelMeaning
Header——BoQ icon and the draft name. A long name is cut; hover to see it in full.
⋯ button——Opens the card menu (Rename, Duplicate, Compare, History, Delete).
MetricNumber of tasksБрой задачиHow many positions the draft has. A position placed in two categories counts twice. Deleted positions are not counted.
MetricTotal valueОбща стойностThe grand total of the BoQ, with 2 decimals and thousands grouping.
Footer——The date the draft was created.
Main buttonBudget acceptanceПриемане на бюджетAccepts the whole draft as the investment budget (see below).

Click anywhere on a draft card (outside the buttons) to open it in the BoQ editor at /projects/{project}/drafts/{boq}.

The Drafts page with two draft cards, the plus card and the card menu open
Figure: The Drafts page with the card menu open
  1. The Drafts (Чернови) entry in the project sidebar opens this page.
  2. A draft card shows the draft name, Number of tasks and Total value.
  3. The ⋯ button opens the card menu with Rename, Duplicate, Compare, History and Delete.
  4. The Budget acceptance button accepts the whole draft as the budget; it is inactive while any position has no price.
  5. The + card creates a new budget draft.

How to create a new budget draft

  1. On the Drafts page, click the + card. You need Offers at Edit; without it a permission message appears.
  2. In the dialog Create new draft (Създаване на нова чернова), type the name in Offer name (Име на оферта). The wording "offer" is reused from the Offers page.
  3. To start from an existing draft, click its card under the text "The new offer can be created based on an existing one and will use its work items." The selected card shows a ✓. Click it again to deselect. A card with a lock warning icon has an unfinished current version; the tooltip says the system will finalize it automatically.
  4. Click Create (Създай), or press Enter. Escape or Cancel (Отказ) closes the dialog. Create stays inactive while the name is empty.

Without a selected template, an empty budget draft is created and the toast Task list "{name}" created successfully appears. With a selected template, the chosen draft is copied under the new name as a background job titled Duplicate BoQ (Дублиране на КСС); the list refreshes when the job finishes.

The Create new draft dialog with a name typed and one existing draft selected as template
Figure: Creating a new budget draft from an existing one
  1. The Offer name field for the new draft.
  2. A template card of an existing draft; the selected one shows a ✓.
  3. Create creates the draft (inactive while the name is empty); Cancel closes the dialog.

The card menu

Item (EN)Item (BG)What it doesNeeds
RenameПреименувайTurns the name into an input with ✓ (save) and ✕ (cancel). Enter saves, Escape cancels.Offers, Edit
DuplicateДублирайOpens the Duplicate dialog to copy the draft from a chosen version.Offers, Edit
CompareСравниOpens the Compare drafts page. Inactive unless the project has at least 2 drafts.—
HistoryИсторияOpens the right-hand panel History - {name} with the version timeline of the draft.—
DeleteИзтрийPermanently deletes the draft after a confirmation.Offers, Edit

How to rename a draft

  1. On the Drafts page, click ⋯ on the card, then Rename (Преименувай).
  2. Type the new name and press Enter or click ✓.

Name rules on the Drafts page: the name is required, 2 to 50 characters long, and may not contain script, angle brackets, --, ; or ... The messages are Required field, The name must be at least 2 characters, The name must be at most 50 characters and The name contains malicious content. On success the toast says Task list renamed to "{name}".

How to duplicate a draft

  1. On the Drafts page, click ⋯ → Duplicate (Дублирай).
  2. In the dialog Duplicate offer (Дублиране на оферта), pick the version in Version to duplicate (Версия за дублиране). The newest version is marked (latest). A read-only preview of the BoQ at that version is shown below.
  3. Click Duplicate (Дублирай).

The copy is named "original name (Copy)" — the suffix "(Copy)" is in English in both languages; rename the copy afterwards if you need to. Duplication runs as the background job Duplicate BoQ (Дублиране на КСС) and copies the positions, quantities, prices and resource analyses of the chosen version. The copy is an independent document.

How to delete a draft

  1. On the Drafts page, click ⋯ → Delete (Изтрий).
  2. In the confirmation Delete offer (Изтриване на оферта) — "Are you sure you want to permanently delete this BoQ? This action cannot be undone." — click Delete (Изтрий).
  3. While the draft is being deleted you see the message Deleting... (Изтриване...). Until it finishes, Delete and Duplicate do nothing for that draft — the same applies while it is being duplicated or accepted as the budget.

Version history of a draft

Choose History (История) in the card menu to open the panel History - {name}. It lists the versions of the draft, newest first. Each entry shows Version N, Total value with the currency, and a status chip. Inside the BoQ editor the same panel also has a Preview (Прегледай) button on each version; on the Drafts page it does not. When there are no versions yet the panel says No data to show (Няма данни за показване).

Status (EN)Status (BG)MeaningWhat you can do next
ProcessingОбработва сеThe current version is open and being edited.Edit; save the version when ready.
Bid request baseБаза на запитванеThe first finished version (the base). For an offer created from an accepted offer request, it is the untouched copy of what the client sent.Edit: the first change opens version 2 without a warning.
CompletedЗавършенаA later version that was saved (locked).Edit: the change opens a new version after a warning.
SentИзпратенаAn offer that was submitted to the client. Sending locks the version.Wait for the client; prepare an update if asked.
Update requestedЗаявена актуализацияThe client asked for a corrected offer.Edit and send a new version.

For offers, the timeline also shows Offer sent, Update sent and Update request entries. See Versions, comparing and locking.

The History panel opened from a draft card with versions and status chips
Figure: The version history of a draft
  1. History in the card menu opens the panel History - {name}.
  2. A Version N entry with its Total value.
  3. The status chip of the version, for example Bid request base or Completed.

Accepting a budget draft

Accepting a draft turns it into the project's investment budget and moves the project into the execution phase. The Budget acceptance (Приемане на бюджет) button on the draft card accepts the whole draft. To accept only the priced part, open the draft and use Accept part of the budget (Приемане на част от бюджета) in the editor; see Partial acceptance.

The Budget acceptance button on the Drafts page is inactive when:

  • the draft total is 0 or less;
  • any position has no unit price. The tooltip then says "{count} items still have no price, so the whole budget cannot be accepted. Open the draft and accept only the priced part.";
  • an acceptance is already running.

How to accept the whole draft

  1. On the Drafts page, click Budget acceptance (Приемане на бюджет) on the draft card. You need Execution (Изпълнение) at Edit.
  2. Read the confirmation: "After locking you will no longer be able to make changes. To make edits you will need to create a new bill of quantities. Are you sure you want to continue?"
  3. Click Yes (Да). If the current version is not locked yet, BuildColab locks it first, then accepts it.
  4. On success you land on the project page and see Budget accepted successfully (Бюджетът е приет успешно).

The "Draft - budget changes" card

After a partial acceptance, the positions you left out move into a draft of the next budget. In the execution phase, the Drafts page shows it as the card Draft - budget changes (Чернова - промени по бюджет):

  • While it is being prepared, the card says "The draft with the lines not yet accepted is being prepared. You can open it in a moment." and the button reads Being prepared… (Подготвя се…).
  • When it is ready, the card says "The lines not yet accepted into the budget. Open the draft to finish and accept them." Click Open (Отвори).

In that draft, positions already in the budget carry the pill Accepted (Приета). If you change one, the change goes into the budget with the next acceptance. You accept the rest with Accept part of the budget or Budget acceptance; each acceptance adds a new version to the budget. See Partial acceptance.

Other places where BoQs are listed

  • Offers (Оферти) — a contractor's offers, grouped by offer request, with lock, rename, duplicate, compare, history and delete actions. See Preparing and submitting an offer.
  • Budget (Бюджет) — the accepted investment budget. See Investment budget.
  • Contracts with contractors (Договори с изпълнители) — the BoQs of signed subcontracts. See Costs.
  • Inside any BoQ editor, click the BoQ name at the top to switch to any other BoQ of your company in the same project.

Common questions

Why is the Budget acceptance button gray?

The Budget acceptance button on a draft card is inactive while the draft total is 0, while any position has unit price 0, or while an acceptance is already running. Hover the button to see how many positions are unpriced. Either price them, or open the draft and accept only the priced part with Accept part of the budget.

Why is Compare inactive in the card menu?

Compare (Сравни) needs at least two budget drafts in the project. Create or duplicate a second draft first.

What happens to my other drafts when I accept one?

They are deleted. Accepting a budget draft deletes every other budget draft of your company on that project. Duplicate a draft first if you need to keep a copy, or export it to Excel.

Can I restore a deleted draft?

No. Deleting a BoQ from the Drafts page is permanent. Export a copy before deleting if you might need the data later.

Why does the copy end with "(Copy)" in English?

The duplicate is always named "original name (Copy)", in both interface languages. Rename it with ⋯ → Rename.

Why does renaming say "The name must be at most 50 characters"?

BoQ names on the Drafts page are limited to 2–50 characters. The create dialog does not check the length, so a longer name can be created but must be shortened the next time you rename it.

Why can't I see the Drafts page as a contractor?

Budget drafts exist only on the investor side. A contractor prepares offers on the Offers (Оферти) page; the editor and the card menu work the same way.

Delete failed with "Error deleting the BoQ". Why?

The BoQ is in use: it has an accepted contract, or some of its positions are committed in an active subcontract. Such BoQs cannot be deleted.