Das Benutzerhandbuch ist auf Englisch und Bulgarisch verfügbar. Sie lesen die englische Fassung.

How a payment application works

Auf dieser Seite
  1. The two sides of a payment application
  2. What a report contains
  3. Executed to date, remaining and the contract cap
  4. Turns and rounds
  5. Statuses
  6. All actions at a glance
  7. Several reports on one contract
  8. What approval changes
  9. When the contract changes
  10. Permissions and plan
  11. Common questions
  12. Related
WhereThe Reports (Отчети) panel of a contract (button on the contract's bill of quantities (BoQ) page or on the Contract details page); the report page /projects/{project}/payment-applications/{report}/draft (draft) or /projects/{project}/payment-applications/{report}/review (submitted and closed reports).
Who canReports (Отчети) at View (Преглед) to see reports, at Edit (Редакция) to act on them. Paid plan or trial. Your company must be one of the two parties of the contract.
RelatedCreating and submitting, Reviewing, approving, countering, rejecting, Contracts: signing, details and history, All statuses explained

The two sides of a payment application

Every payment application belongs to exactly one signed contract, and the contract decides who does what:

SideWho it isWhat it does with reports
Contractor (изпълнител)The company that received the contract and does the work, for example a subcontractor, or a general contractor towards the investor.Creates the report, enters the quantities for the period, adds remarks, files and positions outside the contract, chooses the assignee and submits it. Sees its own drafts.
Client (възложител)The company that awarded the contract and pays for the work.Receives the submitted report, reviews it, approves it, sends a counter-proposal or rejects it. Never sees the contractor's drafts.

Exception: when the contractor is a self-managed subcontractor without its own BuildColab users, the client prepares and finalizes the report on its behalf. See External payment applications.

In the report registers, the same report shows a different Type (Тип) for each side: Budget (Бюджет) for the contractor, who bills its client, and Cost (Разход) for the client, who pays its contractor.

What a report contains

  • The contract's positions. When a report is created, BuildColab copies every position of the contract's BoQ, at the BoQ version the contract was signed on (or the version of its latest change order), with its contracted quantity and unit price. You do not pick positions; you only enter quantities.
  • The quantity for the period. Every position starts at 0. The contractor enters how much was done in this period, in the This period (За периода) column group. Value = quantity × contract unit price.
  • Remarks. Each position has its own REMARK (ЗАБЕЛЕЖКА) cell, separate from the position's note in the BoQ. Both companies see the remarks.
  • Files. Measurement protocols, photos or invoices attached to the report. Both companies can see, download and attach them at any status.
  • Positions outside the contract. Optional extra work that the contract does not cover, priced in the report. See Positions outside the contract.
  • Assignee. The person in the preparing company who is responsible for the report.
  • Total. The sum of the period values of all positions, shown as Total: (Общо:) in the report header.

Executed to date, remaining and the contract cap

Each report shows three column groups next to the contract data:

Column groupMeaning
This period (За периода)Quantity and value claimed in this report.
Executed to date (Изпълнено до момента)Quantity and value already approved in other reports of the same contract. It is the sum of all approved reports, whatever order they were approved in. Drafts and submitted reports do not count until they are approved.
Remaining (Остатък)Contracted quantity − (executed to date + this period). It can be negative only on a re-measurable contract.

Whether a position may be billed beyond its contracted quantity depends on the contract type chosen when the contract was signed:

  • Fixed-price contracts (and older contracts without a type) are capped. You cannot enter a period quantity that takes a position past its contracted quantity; the cell shows Maximum: {max} (Максимум: {max}). More work needs a change order. Once the approved reports cover the whole contract value, Create report is disabled with the tooltip "The contract is fully claimed — all contracted quantities have already been approved." (Договорът е напълно усвоен — всички договорени количества вече са одобрени.)
  • Unit-price (re-measurable) contracts are not capped. You may bill more than the contracted quantity. The position turns red with "Over the contracted quantity by {qty}" (Над договорното количество с {qty}), and % billed in the register can exceed 100.

The cap applies everywhere a quantity enters a report: typing, Certify full quantity, Excel import and pulling from subcontractor reports. It is checked again at approval, so two reports approved at the same time cannot together exceed the contracted quantity; the second approval is refused with a message that another payment application was approved first.

Turns and rounds

While a report is submitted, only one company can act on it at a time. That company "has the turn".

  • After Submit for Approval (Изпрати за одобрение) the turn passes to the client.
  • The company with the turn can approve, reject or send a counter-proposal. A counter-proposal changes quantities, remarks or new positions and passes the turn to the other company.
  • The company without the turn waits. It sees "Waiting on {company}" (Изчаква се {company}) and can only Withdraw (Оттегли) its own proposal.
  • The company with the turn sees "Waiting on your response" (Изчаква се вашият отговор). In the Reports panel its card shows Your turn (Вашият ред); the other company sees Counterparty's turn (Ред на контрагента).
Submitted payment application seen by the contractor, with the Waiting on bar and the Withdraw button
Figure: A submitted report seen by the contractor while the client has the turn.
  1. View history ({count}) (Виж историята ({count})) counts the rounds so far.
  2. Withdraw (Оттегли) is the only action for the company without the turn.
  3. The negotiation bar "Waiting on {company}" (Изчаква се {company}) names the company that has the turn.

Each submission and each counter-proposal is saved as a round, a frozen snapshot of all quantities, remarks and new positions. The first round is called Initial submission (Първоначално подаване); later rounds are Version #{n} (Версия №{n}). Rounds cannot be changed. You can show them as extra columns and compare them; see Reviewing, approving, countering, rejecting. Approval always accepts the latest round.

Statuses

Reports panel with a Submitted and an Approved report card
Figure: Report cards in the Reports panel: one submitted, one approved. A Draft card also has the trash icon Delete draft (Изтрий чернова); a Rejected (Отхвърлен) card has Revise (Ревизирай).
  1. A Submitted (Изпратен) card with the turn badge, here Counterparty's turn (Ред на контрагента).
  2. An Approved (Одобрен) card. It cannot be changed any more.
Status (EN / BG)MeaningWhat can happen next
Draft / ЧерноваThe contractor is preparing the report. Only the contractor sees it (for a self-managed subcontractor, the client who prepares it).Edit, Submit for Approval, or Delete draft. For a self-managed subcontractor: Finalize.
Submitted / Изпратен; the client sees Received / ПолученThe report is under review. One status, two labels: the company that sent it sees "Submitted", the receiving company "Received".The company with the turn: Approve, Counter, Reject. The other company: Withdraw.
Approved / ОдобренFinal. The quantities count in "Executed to date" of the contract and as certified cost for the client.Nothing. Only a recorded report of a self-managed subcontractor can be voided, and only the latest.
Rejected / ОтхвърленDeclined with a mandatory reason, shown at the top of the report as Rejection reason: (Причина за отхвърляне:).The contractor can Revise it into a new draft, if it is the newest report on the contract and the contract has not changed since.
Withdrawn / ОттегленPulled back by the company that sent the current proposal. Final; the round history is kept.Nothing on this report. Start a new report, also from one of its rounds with New from a previous version.

All actions at a glance

Action (EN / BG)WhoStatus changeWho is told
Create report / Създай отчетContractor, Editnew DraftNobody
Submit for Approval / Изпрати за одобрениеContractor, EditDraft → Submitted; round 1Client: e-mail "{contractor} sent payment application No. {n} for approval" („{contractor} изпрати отчет №{n} за одобрение“) and in-app "Pay application #{n} for {contract} is awaiting approval ({amount})"
Counter → Send counter-proposal / Насрещно предложение → Изпрати насрещно предложениеCompany with the turnstays Submitted; new round; turn flipsOther company: e-mail "{company} made a counter-proposal on payment application No. {n}" („{company} направи насрещно предложение по отчет №{n}“) and in-app "Counter-proposal on pay application #{n}"
Approve / ОдобриCompany with the turnSubmitted → ApprovedOther company: e-mail "Payment application No. {n} was approved by {company}" („Отчет №{n} беше одобрен от {company}“); in-app "Pay application #{n} was approved"
Reject / ОтхвърлиCompany with the turnSubmitted → RejectedOther company: e-mail "Payment application No. {n} was rejected by {company}" („Отчет №{n} беше отхвърлен от {company}“); in-app "Pay application #{n} was rejected"
Withdraw / ОттеглиCompany that sent the current proposalSubmitted → WithdrawnOther company: e-mail "{company} withdrew payment application No. {n}" („{company} оттегли отчет №{n}“); in-app "Pay application #{n} was withdrawn"
Revise / РевизирайContractor, EditRejected stays; new Draft copied from itNobody
Delete draft / Изтрий черноваContractor, EditDraft removedNobody
Assignee change / ОтговорникPreparing company, Edit, Draft onlynoneThe new assignee: e-mail "You are the assignee of payment application No. {n}" („Вие сте отговорник по отчет №{n}“) and in-app "You have been assigned as approver for pay application #{n}"
Record report, Finalize, Void report / Запиши отчет, Финализирай, Анулирай отчетClient of a self-managed subcontractorDraft → Approved; Approved → removedNobody

E-mails go to the other company's e-mail address (from its company profile) and link straight to the report. An e-mail is written in Bulgarian or English: in the saved profile language of the BuildColab account with that address; if there is none, in the language of the user who acted, and by default in Bulgarian. The assignment e-mail goes to the assigned person. In-app notifications go to project members with the Reports permission; see Notifications and their settings.

Several reports on one contract

A contract usually has one report per period: Report #1 for the first month, Report #2 for the second, and so on. BuildColab also lets several drafts and several submitted reports exist on the same contract at the same time. Each has its own number, its own negotiation and its own approval. Approval order does not matter: executed-to-date is always the sum of all approved reports.

Two limits keep the chain consistent: only the newest report on a contract can be revised after rejection, and for a self-managed subcontractor only one report can be open at a time.

What approval changes

  • The report's quantities are stamped as approved and count in Executed to date of every later report on the contract.
  • On the client's side, the approved value appears as certified in the budget and the financial dashboard. See Financial dashboard: committed, certified, margin.
  • Positions outside the contract that the report carried are merged into the contract as a new BoQ version. An open change-order draft on the contract is superseded and has to be created again from the updated contract. See Positions outside the contract.
  • The contractor gets the notification "Your pay application was approved. Invoicing is next." Invoicing itself happens outside BuildColab.

When the contract changes

A change order creates a new contract version. Reports created after it use the new contract positions, quantities and prices. Older reports keep showing the BoQ version they were made on. A rejected report made before the change cannot be revised; create a new report instead.

Permissions and plan

What you want to doWhat you need
Open the Reports panel, a report, the registers and the summary; exportReports (Отчети) at View (Преглед)
Create, edit, submit, approve, counter, reject, withdraw, revise, delete a draft, attach files, set the assignee, record, finalize, voidReports at Edit (Редакция), plus being the right side of the contract (and, for approve, counter and reject, having the turn)
Open the resource analysis of a position outside the contractResource analysis (Ресурсен анализ) at View
Any of the aboveA paid plan or trial. Reports is not part of the Free plan; a member without a seat license gets only the Free features.

Without the permission, the Reports button shows a permission message instead of the panel, and the Report Register sidebar entry is locked. See Permission reference.

Common questions

Who submits a payment application, the client or the contractor?

The contractor, meaning the company that received the contract and does the work. The client only reviews. The one exception is a self-managed subcontractor, whose reports the client records itself.

Why does the same report say "Submitted" for me and "Received" for my client?

It is the same status seen from the two sides. The company that sent it sees Submitted (Изпратен), the receiving company Received (Получен).

Why can't I enter more than the contracted quantity?

The contract is fixed-price (or has no type), so it is capped and shows Maximum: {max}. Billing more requires a change order that raises the quantity. Unit-price contracts allow over-runs.

Can my client change my quantities?

Not directly. When the client has the turn it can send a counter-proposal with different quantities. You then accept it with Approve, counter again or reject it. Every version is kept in the history.

Can an approved report be reopened?

No. Approval is final. Correct the difference in the next report or through a change order. Only a recorded report of a self-managed subcontractor can be voided, and only the latest one.

Can two reports be open on the same contract?

Yes, for normal contracts. Several drafts and several submitted reports can coexist, each approved separately. For a self-managed subcontractor, only one at a time.

Where do VAT, retention and the advance come in?

They do not. Reports have no VAT, retention or advance deductions; those values are kept on the contract only.

Who gets e-mails about a report?

The other company's e-mail address gets an e-mail when a report is submitted, countered, approved, rejected or withdrawn; the assigned person gets one when assigned. Each e-mail is in the recipient's profile language; without one, in the language of the user who acted (Bulgarian by default). Reports of self-managed subcontractors send no e-mails.